Construction update September 2018
- The environmental impact assessment has been approved.
- Request for a construction permit has already been filed under section 39.
- Expected Completion Date: May 2019
- 75.22% of Overall construction work completed
# | Percentage Completed | Construction Work Progress | |
---|---|---|---|
1 | Strutural work | 99.40% |
B1 & B2 floor = 100% completed L1-L55 floor = 100% completed Roof feature construction is 95% complete. |
2 | Systems installation | 72.89% |
Electrical and communication system = 67.63% completed Sanitary, plumbing and fire protection system = 78.42% completed Air conditioning and ventilation system = 76.32%completed |
3 | Architectural work | 75.61% |
Public area = 86.30% completed Common area = 73.89% completed Guest Room = 99.05% completed Façade – Precast Wall = 57.40% completed |
4 | Interior work | 58.25% |
Guest Room construction is 58.72%complete. Public Area construction is 57.46% complete. |