Construction update September 2016

Construction update September 2016

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 4.60% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 14.27% In the process of soil protection work.
2 Systems installation - -
3 Architectural wor - -