Construction update October 2016
- The environmental impact assessment has been approved.
- Request for a construction permit has already been filed under section 39.
- Expected Completion Date: May 2019
- 4.82% of Overall construction work completed
# | Percentage Completed | Construction Work Progress | |
---|---|---|---|
1 | Strutural work | 14.99% | In the process of soil protection work. |
2 | Systems installation | - | - |
3 | Architectural work | - | - |