Construction update November 2017
- The environmental impact assessment has been approved.
- Request for a construction permit has already been filed under section 39.
- Expected Completion Date: May 2019
- 28.13 % of Overall construction work completed
# | Percentage Completed | Construction Work Progress | |
---|---|---|---|
1 | Strutural work | 65.01% |
Basement 1 – 2 = 100% completed 1st floor = 90% completed 1st M - 7th floor = 100% completed 8th – 9th floor = 75% completed 9th M floor = 60% completed 10th – 27th floor = 100% completed 28th – 31st floor = 50% completed |
2 | Systems installation | 9.86% |
Electrical and communication system = 5.16% completed Sanitary, plumbing and fire protection system = 16.00% completed Air conditioning and ventilation system = 15.41% completed |
3 | Architectural work | 15.06% |
Public area = 31.68% completed Common area = 12.19% completed Guest Room = 29.57% completed Façade – Precast Wall = 7.25% completed |