Construction update May 2019

Construction update May 2019

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 96.50% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 100% B1 & B2 floor = 100% completed
L1-L55 floor = 100% completed
Roof feature construction is 100% complete.
2 Systems installation 98.49% Electrical and communication system = 98.86% completed
Sanitary, plumbing and fire protection system = 98.43% completed
Air conditioning and ventilation system = 98.64% completed
3 Architectural work 98.83% Public area = 97.81% completed
Common area = 98.89% completed
Guest Room = 100% completed
Façade – Precast Wall = 98.92% completed
4 Interior work 98.78% Guest Room construction is 98.25% complete.
Public Area construction is 98.18% complete.