Construction update May 2018
- The environmental impact assessment has been approved.
- Request for a construction permit has already been filed under section 39.
- Expected Completion Date: May 2019
- 48.35% of Overall construction work completed
# | Percentage Completed | Construction Work Progress | |
---|---|---|---|
1 | Strutural work | 90.39% |
Basement 1 – 2 = 100% completed L1-L32M floor = 100% completed L33 floor = 80% completed L34-L49 floor = 100% completed |
2 | Systems installation | 44.29% |
Electrical and communication system = 38.52% completed Sanitary, plumbing and fire protection system = 51.24% completed Air conditioning and ventilation system = 46.69% completed |
3 | Architectural work | 45.67% |
Public area = 69.64% completed Common area = 25.17% completed Guest Room = 76.46% completed Façade – Precast Wall = 39.57% completed |
4 | Interior work | 21.96% |
Guest Room construction is 22.36% complete. Public Area construction is 21.26% complete. |