Construction update March 2019

Construction update March 2019

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 90.40% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 99.94% B1 & B2 floor = 100% completed
L1-L55 floor = 100% completed
Roof feature construction is 99.91% complete.
2 Systems installation 94.95% Electrical and communication system = 94.90% completed
Sanitary, plumbing and fire protection system = 95.00% completed
Air conditioning and ventilation system = 95.00% completed
3 Architectural work 97.80% Public area = 89.21% completed
Common area = 97.49% completed
Guest Room = 100% completed
Façade – Precast Wall = 97.01% completed
4 Interior work 86.78% Guest Room construction is 90.85% complete.
Public Area construction is 82.53% complete.
Share this Post: