Construction update March 2018
- The environmental impact assessment has been approved.
- Request for a construction permit has already been filed under section 39.
- Expected Completion Date: May 2019
- 46.06 % of Overall construction work completed
# | Percentage Completed | Construction Work Progress | |
---|---|---|---|
1 | Strutural work | 82.24% |
Basement 1 – 2 = 100% completed 1st floor = 90% completed 1st M - 9th floor = 100% completed 9th M floor = 90% completed 10th – 31st floor = 100% completed 32nd M floor = 70% completed 34th – 41st floor = 100% completed 42nd floor = 50% completed |
2 | Systems installation | 31.38% |
Electrical and communication system = 25.29% completed Sanitary, plumbing and fire protection system = 37.17% completed Air conditioning and ventilation system = 36.35% completed |
3 | Architectural work | 33.87% |
Public area = 50.67% completed Common area = 18.62% completed Guest Room = 59.61% completed Façade – Precast Wall = 27.09% completed |
4 | Interior work | 7.62% |
Guest Room construction is 10.91% complete. Public Area construction is 1.94% complete. |