Construction update May 2018
- The environmental impact assessment has been approved.
- Request for a construction permit has already been filed under section 39.
- Expected Completion Date: May 2019
- 49.27% of Overall construction work completed
# | Percentage Completed | Construction Work Progress | |
---|---|---|---|
1 | Strutural work | 94.58% |
B2 & B1 floor construction is 100% complete. L1-L32M floor construction is 100% complete. L33 floor construction is 80% complete. L34-L53 floor construction is 100% complete. |
2 | Systems installation | 49.20% |
Electrical and communication system construction is 44.18% complete. Sanitary, plumbing and fire protection system construction is 55.36% complete. Air conditioning and ventilation system construction is 51.14% complete. |
3 | Architectural work | 51.02% |
Public area construction is 69.64% complete. Common area construction is 32.07% complete. Guest Room construction is 83.05% complete. Façade – Precast wall construction is 42.75% complete. |
4 | Interior work | 30.86% |
Guest Room construction is 32.08% complete. Public Area construction is 28.75% complete. |