Construction update January 2018
- The environmental impact assessment has been approved.
- Request for a construction permit has already been filed under section 39.
- Expected Completion Date: May 2019
- 30.87 % of Overall construction work completed
# | Percentage Completed | Construction Work Progress | |
---|---|---|---|
1 | Strutural work | 74.43% |
Basement 1 – 2 = 100% completed 1st floor = 90% completed 1st M - 7th floor = 100% completed 8th – 9th floor = 75% completed 9th M floor = 60% completed 10th – 31st floor = 100% completed 32nd M floor = 50% completed 34th – 37th floor = 50% completed |
2 | Systems installation | 19.95% |
Electrical and communication system = 11.41% completed Sanitary, plumbing and fire protection system = 27.07% completed Air conditioning and ventilation system = 27.93% completed |
3 | Architectural work | 26.21% |
Public area = 47.59% completed Common area = 16.82% completed Guest Room = 51.69% completed Façade – Precast Wall = 13.32% completed |
4 | Interior work | 2.69% | Guest Room = 4.25% completed |