Construction update febuary 2019
- The environmental impact assessment has been approved.
- Request for a construction permit has already been filed under section 39.
- Expected Completion Date: May 2019
- 89.30% of Overall construction work completed
# | Percentage Completed | Construction Work Progress | |
---|---|---|---|
1 | Strutural work | 99.94% |
B1 & B2 floor = 100% completed L1-L55 floor = 100% completed Roof feature construction is 99.91% complete. |
2 | Systems installation | 94.04% |
Electrical and communication system = 94.16% completed Sanitary, plumbing and fire protection system = 95.00% completed Air conditioning and ventilation system = 92.26% completed |
3 | Architectural work | 97.80% |
Public area = 89.21% completed Common area = 97.49% completed Guest Room = 100% completed Façade – Precast Wall = 97.01% completed |
4 | Interior work | 81.80% |
Guest Room construction is 87.69% complete. Public Area construction is 78.45% complete. |