Construction update September 2018
- The environmental impact assessment has been approved.
- Request for a construction permit has already been filed under section 39.
- Expected Completion Date: May 2019
- 72.20% of Overall construction work completed
# | Percentage Completed | Construction Work Progress | |
---|---|---|---|
1 | Strutural work | 98.98%% |
B1 & B2 floor = 100% completed L1-L55 floor = 100% completed L33 floor = 90% completed Roof feature construction is 85% complete. |
2 | Systems installation | 64.93% |
Electrical and communication system = 60.36% completed Sanitary, plumbing and fire protection system = 69.27% completed Air conditioning and ventilation system = 68.62%completed |
3 | Architectural work | 61.59% |
Public area = 78.57% completed Common area = 49.78% completed Guest Room = 95.36% completed Façade – Precast Wall = 44.75% completed |
4 | Interior work | 50.25% |
Guest Room construction is 51.51%complete. Public Area construction is 48.07% complete. |