Construction update August 2017
- The environmental impact assessment has been approved.
- Request for a construction permit has already been filed under section 39.
- Expected Completion Date: May 2019
- 15.45% of Overall construction work completed
# | Percentage Completed | Construction Work Progress | |
---|---|---|---|
1 | Strutural work | 48.66% |
Basement 1 – 2 = 100% completed 1st floor = 90% completed 1st M - 7th floor = 100% completed 8th – 9th floor = 75% completed 9th M floor = 60% completed 10th floor = 75% completed 11th – 17th floor = 50% completed |
2 | Systems installation | 1.55% |
Electrical and communication system = 1.24% completed Sanitary, plumbing and fire protection system = 2.50% completed Air conditioning and ventilation system = 1.06% completed |
3 | Architectural work | 2.05% |
Common areas = 5.34% completed Façade – Precast wall = 0.54% completed |