Construction update April 2019
- The environmental impact assessment has been approved.
- Request for a construction permit has already been filed under section 39.
- Expected Completion Date: May 2019
- 95.30% of Overall construction work completed
# | Percentage Completed | Construction Work Progress | |
---|---|---|---|
1 | Strutural work | 100% |
B1 & B2 floor = 100% completed L1-L55 floor = 100% completed Roof feature construction is 100% complete. |
2 | Systems installation | 97.65% |
Electrical and communication system = 98.06% completed Sanitary, plumbing and fire protection system = 97.43% completed Air conditioning and ventilation system = 97.04% completed |
3 | Architectural work | 98.53% |
Public area = 89.21% completed Common area = 98.19% completed Guest Room = 100% completed Façade – Precast Wall = 98.42% completed |
4 | Interior work | 91.28% |
Guest Room construction is 98.25% complete. Public Area construction is 87.48% complete. |