Construction update April 2019

Construction update April 2019

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 95.30% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 100% B1 & B2 floor = 100% completed
L1-L55 floor = 100% completed
Roof feature construction is 100% complete.
2 Systems installation 97.65% Electrical and communication system = 98.06% completed
Sanitary, plumbing and fire protection system = 97.43% completed
Air conditioning and ventilation system = 97.04% completed
3 Architectural work 98.53% Public area = 89.21% completed
Common area = 98.19% completed
Guest Room = 100% completed
Façade – Precast Wall = 98.42% completed
4 Interior work 91.28% Guest Room construction is 98.25% complete.
Public Area construction is 87.48% complete.