Construction Progress Update as of September 2018

28 Sep 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: MAY 2019
  • Piling works completed 
  • 50.95% of Overall construction work completed


      Percentage Completed Construction Work Progress
    1) Structural work

    87.23%

    Mat Foundation, Footing, WT
    Slip Form 39th M floor

    Column 39th M   floor

    Slab 38th  M floor

    Stairs ST-01, 32nd floor,
    02 38th M floor,
    03 7th  floor,
    06, 5th - 6th  floor

    2) Systems installation

    39.42%

    Electrical Sleeve and Sanitary System for Slab,
    Column 39th M  floor,
    Slip Form 39th M floor,
    Stair 38th M floor,
    Sprinker Air 16th – 22nd    floor

    3) Architectural work 

    28.82%

    Curb, Stiffener & Lintel 34th   floor,
    Curtain Wall 8th – 16th floor,
    Block and Wall Plastering 22nd – 33rd floor,
    Setting Out Line 34th floor