Construction update October 2018

30 Oct 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: MAY 2019
  • Piling works completed
  • 59.38% of Overall construction work completed

 

 

Percentage Completed

Construction Work Progress

1) Structural work

92.13%

Mat Foundation, Footing, WT Slip Form Roof floor
Column 39th M floor Slab Roof floor
Stairs ST-01, 36th  floor, 02 Roof floor, 03 7th  floor, 06, 5th - 6th  floor

2) Systems installation

48.66%

Electrical Sleeve and Sanitary System for Slab,
Column 39th M  floor, Slip Form Roof floor, Stair Roof floor,
Sprinker Air 31st  floor

3) Architectural work

36.55%

Curb, Stiffener & Lintel 35th floor,
Curtain Wall 8th – 16th floor,
Block and Wall Plastering 25th – 34th floor,
Setting Out Line 35th floor