30 Nov 2018
Percentage Completed |
Construction Work Progress |
|
1) Structural work |
99.00% |
Mat Foundation, Footing, WT |
2) Systems installation |
55.44 |
Electrical Sleeve and Sanitary System for Slab, |
3) Architectural work |
46.56 |
Curb, Stiffener & Lintel 36 M floor, |