Construction update November 2018

30 Nov 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: MAY 2019
  • Piling works completed
  • 67.00% of Overall construction work completed

 

 

Percentage Completed

Construction Work Progress

1) Structural work

99.00%

Mat Foundation, Footing, WT
Slip Form Roof floor
Column Roof floor
Slab Roof floor
Stairs ST-01, 36th  floor,
02 Roof floor

2) Systems installation

55.44

Electrical Sleeve and Sanitary System for Slab,
Column Roof floor,
Slip Form Roof floor,
Stair Roof floor,
Sprinker Air 32nd  floor

3) Architectural work

46.56

Curb, Stiffener & Lintel 36 M  floor,
Curtain Wall 8th – 20th   floor,
Block and Wall Plastering 32nd– 36th M  floor,
Tiling 8th – 15th  floor