Construction update May 2019

14 Jun 2019

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: MAY 2019
  • Piling works completed
  • 94.40% of Overall construction work completed

 

 

Percentage Completed

Construction Work Progress

1) Structural work

100%

Slip Form, Column, Slab  and Stairs Roof floor

2) Systems installation

94.40%

Stair Roof floor
Sprinker Air 34-35 floor

3) Architectural work

80.80%

Curtain Wall 34th – 35th floor,
Block and Wall Plastering 38th – 39th M floor,
Tiling 29th – 33rd floor