Construction update March 2019

15 Apr 2019

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: MAY 2019
  • Piling works completed
  • 87.78% of Overall construction work completed

 

 

Percentage Completed

Construction Work Progress

1) Structural work

100%

Mat Foundation, Footing, WT
Slip Form Roof floor
Column Roof floor
Slab Roof floor
Stairs Roof floor

2) Systems installation

87.52%

Electrical Sleeve and Sanitary System for Slab,
Column Roof floor,
Slip Form Roof floor,
Stair Roof floor,
Sprinker Air 34th   floor

3) Architectural work

75.87%

Curtain Wall 33rd – 35th   floor,
Block and Wall Plastering 38th – 39th M  floor,
Tiling 25th – 33rd floor