Construction update January 2019

4 Feb 2019

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: MAY 2019
  • Piling works completed
  • 78.75% of Overall construction work completed

 

 

Percentage Completed

Construction Work Progress

1) Structural work

99.25%

Mat Foundation, Footing, WT
Slip Form Roof floor
Column Roof floor
Slab Roof floor
Stairs ST-01, 36th  floor,
02 Roof floor

2) Systems installation

78.42%

Electrical Sleeve and Sanitary System for Slab,
Column Roof floor,
Slip Form Roof floor,
Stair Roof floor,
Sprinker Air 29th – 34th floor

3) Architectural work

58.58%

Curb, Stiffener & Lintel 37 M  floor,
Curtain Wall 29th – 35th   floor,
Block and Wall Plastering 36th – 37th M floor,
Tiling 29th floor