Construction update February 2019

4 Mar 2019

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: MAY 2019
  • Piling works completed
  • 83.25% of Overall construction work completed

 

 

Percentage Completed

Construction Work Progress

1) Structural work

99.30%

Mat Foundation, Footing, WT
Slip Form Roof floor
Column Roof floor
Slab Roof floor
Stairs ST-01, 36th  floor, 
02 Roof floor

2) Systems installation

78.42%

Electrical Sleeve and Sanitary System for Slab, 
Column Roof floor, 
Slip Form Roof floor,
Stair Roof floor,
Sprinker Air 34th floor

3) Architectural work

72.03%

Curtain Wall 33rd – 35th   floor,
Block and Wall Plastering 38th – 39th M  floor,
Tiling 25th – 33rd floor