10 Jan 2019
Percentage Completed |
Construction Work Progress |
|
1) Structural work |
99.12% |
Mat Foundation, Footing, WT |
2) Systems installation |
63.80% |
Electrical Sleeve and Sanitary System for Slab, |
3) Architectural work |
54.48% |
Curb, Stiffener & Lintel 36 M floor, |