Construction update December 2018

10 Jan 2019

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: MAY 2019
  • Piling works completed
  • 73.80% of Overall construction work completed

 

 

Percentage Completed

Construction Work Progress

1) Structural work

99.12%

Mat Foundation, Footing, WT
Slip Form Roof floor
Column Roof floor
Slab Roof floor
Stairs ST-01, 36th  floor, 
02 Roof floor

2) Systems installation

63.80%

Electrical Sleeve and Sanitary System for Slab, 
Column Roof floor, 
Slip Form Roof floor,
Stair Roof floor,
Sprinker Air 32nd  floor

3) Architectural work

54.48%

Curb, Stiffener & Lintel 36 M  floor, 
Curtain Wall 8th – 20th   floor,
Block and Wall Plastering 32nd– 36th M  floor, 
Tiling 8th – 15th  floor