Construction Progress Update as of August 2018

30 Aug 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: MAY 2019
  • Piling works completed 
  • 37.79% of Overall construction work completed


      Percentage Completed Construction Work Progress
    1) Structural work

    78.84%

    Mat Foundation, Footing, WT, Slip Form FL.38, Column FL.37M, Slab FL.37, Stair ST-01 FL.30, 02 FL.37, 03 FL.7, 06 FL.5-6

    2) Systems installation

    28.90%

    Electrical Sleeve and Sanitary System For Slab, Column FL.37, Slip Form FL.38, WT FL.7M, Stair FL.37, Sprinker, Air FL.8-18

    3) Architectural work 

    19.58%

    Curb, Stiffener & Lintel FL.32, Precast FL.8-16, Block and Wall Plastering FL.11-32, Setting Out Line FL.3