30 Aug 2018
Percentage Completed | Construction Work Progress | |
1) Structural work |
78.84% |
Mat Foundation, Footing, WT, Slip Form FL.38, Column FL.37M, Slab FL.37, Stair ST-01 FL.30, 02 FL.37, 03 FL.7, 06 FL.5-6 |
2) Systems installation |
28.90% |
Electrical Sleeve and Sanitary System For Slab, Column FL.37, Slip Form FL.38, WT FL.7M, Stair FL.37, Sprinker, Air FL.8-18 |
3) Architectural work |
19.58% |
Curb, Stiffener & Lintel FL.32, Precast FL.8-16, Block and Wall Plastering FL.11-32, Setting Out Line FL.3 |