Construction update September 2018

Construction update September 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 75.22% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 99.40% B1 & B2 floor = 100% completed
L1-L55 floor = 100% completed
Roof feature construction is 95% complete.
2 Systems installation 72.89% Electrical and communication system = 67.63% completed
Sanitary, plumbing and fire protection system = 78.42% completed
Air conditioning and ventilation system = 76.32%completed
3 Architectural work 75.61% Public area = 86.30% completed
Common area = 73.89% completed
Guest Room = 99.05% completed
Façade – Precast Wall = 57.40% completed
4 Interior work 58.25% Guest Room construction is 58.72%complete.
Public Area construction is 57.46% complete.