Construction update october 2018

Construction update october 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 82.11 % of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 99.86% B1 & B2 floor = 100% completed
L1-L55 floor = 100% completed
Roof feature construction is 99.85% complete.
2 Systems installation 81.19% Electrical and communication system = 76.03% completed
Sanitary, plumbing and fire protection system = 87.32% completed
Air conditioning and ventilation system = 76.32%completed
3 Architectural work 87.63% Public area = 89.21% completed
Common area = 82.68% completed
Guest Room = 99.74% completed
Façade – Precast Wall = 82.68% completed
4 Interior work 64.36% Guest Room construction is 62.96%complete.
Public Area construction is 66.78% complete.