Construction update October 2017

Construction update October 2017

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 20.73 % of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 60.02% Basement 1 – 2 = 100% completed
1st floor = 90% completed
1st M - 7th floor = 100% completed
8th – 9th floor = 75% completed
9th M floor = 60% completed
10th – 22nd floor = 100% completed
23rd – 25th floor = 50% completed
2 Systems installation 6.03% Electrical and communication system = 3.26% completed
Sanitary, plumbing and fire protection system = 9.83% completed
Air conditioning and ventilation system = 8.89% completed
3 Architectural work 6.58% Public area = 31.68% completed
Common area = 9.53% completed
Guest Room = 0.11% completed
Façade – Precast Wall = 6.85% completed