Construction update November 2018

Construction update November 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 85.89% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 99.94% B1 & B2 floor = 100% completed
L1-L55 floor = 100% completed
Roof feature construction is 99.91% complete.
2 Systems installation 86.78% Electrical and communication system = 82.85% completed
Sanitary, plumbing and fire protection system = 92.52% completed
Air conditioning and ventilation system = 86.84%completed
3 Architectural work 92.94% Public area = 89.21% completed
Common area = 89.76% completed
Guest Room = 100% completed
Façade – Precast Wall = 90.72% completed
4 Interior work 70.65% Guest Room construction is 71%complete.
Public Area construction is 70.05% complete.