Construction update November 2017

Construction update November 2017

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 28.13 % of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 65.01% Basement 1 – 2 = 100% completed
1st floor = 90% completed
1st M - 7th floor = 100% completed
8th – 9th floor = 75% completed
9th M floor = 60% completed
10th – 27th floor = 100% completed
28th – 31st floor = 50% completed
2 Systems installation 9.86% Electrical and communication system = 5.16% completed
Sanitary, plumbing and fire protection system = 16.00% completed
Air conditioning and ventilation system = 15.41% completed
3 Architectural work 15.06% Public area = 31.68% completed
Common area = 12.19% completed
Guest Room = 29.57% completed
Façade – Precast Wall = 7.25% completed