Construction update May 2018

Construction update May 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 48.35% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 90.39% Basement 1 – 2 = 100% completed
L1-L32M floor = 100% completed
L33 floor = 80% completed
L34-L49 floor = 100% completed
2 Systems installation 44.29% Electrical and communication system = 38.52% completed
Sanitary, plumbing and fire protection system = 51.24% completed
Air conditioning and ventilation system = 46.69% completed
3 Architectural work 45.67% Public area = 69.64% completed
Common area = 25.17% completed
Guest Room = 76.46% completed
Façade – Precast Wall = 39.57% completed
4 Interior work 21.96% Guest Room construction is 22.36% complete.
Public Area construction is 21.26% complete.