Construction update May 2017

Construction update May 2017

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 11.29% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 35.53% 1st floor construction is 90% complete.
2nd-7th floor construction is 50% complete.
8th floor construction is 25% complete.
2 Systems installation - -
3 Architectural work - -