Construction update March 2018

Construction update March 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 46.06 % of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 82.24% Basement 1 – 2 = 100% completed
1st floor = 90% completed
1st M - 9th floor = 100% completed
9th M floor = 90% completed
10th – 31st floor = 100% completed
32nd M floor = 70% completed
34th – 41st floor = 100% completed
42nd floor = 50% completed
2 Systems installation 31.38% Electrical and communication system = 25.29% completed
Sanitary, plumbing and fire protection system = 37.17% completed
Air conditioning and ventilation system = 36.35% completed
3 Architectural work 33.87% Public area = 50.67% completed
Common area = 18.62% completed
Guest Room = 59.61% completed
Façade – Precast Wall = 27.09% completed
4 Interior work 7.62% Guest Room construction is 10.91% complete.
Public Area construction is 1.94% complete.