Construction update June 2018

Construction update May 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 49.27% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 94.58% B2 & B1 floor construction is 100% complete.
L1-L32M floor construction is 100% complete.
L33 floor construction is 80% complete.
L34-L53 floor construction is 100% complete.
2 Systems installation 49.20% Electrical and communication system construction is 44.18% complete.
Sanitary, plumbing and fire protection system construction is 55.36% complete.
Air conditioning and ventilation system construction is 51.14% complete.
3 Architectural work 51.02% Public area construction is 69.64% complete.
Common area construction is 32.07% complete.
Guest Room construction is 83.05% complete.
Façade – Precast wall construction is 42.75% complete.
4 Interior work 30.86% Guest Room construction is 32.08% complete.
Public Area construction is 28.75% complete.