Construction update June 2017

Construction update June 2017

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: June 2019
  • 12.04% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 37.89% 1st floor construction is 90% complete.
2nd-4th floor construction is 75% complete.
5th-9th floor construction is 50% complete.
2 Systems installation - -
3 Architectural work - -