Construction update July 2018

Construction update July 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 69.93% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 95.87% B2 & B1 floor construction is 100% complete.
L1-L32M floor construction is 100% complete.
L33 floor construction is 90% complete.
L34-L55 floor construction is 100% complete.
Roof feature construction is 10% complete.
2 Systems installation 55.75% Electrical and communication system construction is 51.07% complete.
Sanitary, plumbing and fire protection system construction is 60.87% complete.
Air conditioning and ventilation system construction is 58.52% complete.
3 Architectural work 53.03% Public area construction is 76.54% complete.
Common area construction is 33.67% complete.
Guest Room construction is 87.55% complete.
Façade – Precast wall construction is 42.75% complete.
4 Interior work 42.04% Guest Room construction is 44.22% complete.
Public Area construction is 38.27% complete.