Construction update July 2017

Construction update July 2017

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 13.40% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 42.21% Basement 1 – 2 = 100% completed
1st floor = 90% completed
1st M - 5th floor = 100% completed
6th – 8th floor = 75% completed
9th floor = 50% completed
9th M floor = 40% completed
10th – 12th floor = 60% completed
2 Systems installation - -
3 Architectural work - -