Construction update January 2019

Construction update January 2019

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 88.50% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 99.94% B1 & B2 floor = 100% completed
L1-L55 floor = 100% completed
Roof feature construction is 99.91% complete.
2 Systems installation 92.10% Electrical and communication system = 91.75% completed
Sanitary, plumbing and fire protection system = 93.73% completed
Air conditioning and ventilation system = 90.37% completed
3 Architectural work 95.61% Public area = 89.21% completed
Common area = 95.09% completed
Guest Room = 100% completed
Façade – Precast Wall = 93.06% completed
4 Interior work 75.45% Guest Room construction is 76.44% complete.
Public Area construction is 74.65% complete.