Construction update January 2018

Construction update January 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 30.87 % of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 74.43% Basement 1 – 2 = 100% completed
1st floor = 90% completed
1st M - 7th floor = 100% completed
8th – 9th floor = 75% completed
9th M floor = 60% completed
10th – 31st floor = 100% completed
32nd M floor = 50% completed
34th – 37th floor = 50% completed
2 Systems installation 19.95% Electrical and communication system = 11.41% completed
Sanitary, plumbing and fire protection system = 27.07% completed
Air conditioning and ventilation system = 27.93% completed
3 Architectural work 26.21% Public area = 47.59% completed
Common area = 16.82% completed
Guest Room = 51.69% completed
Façade – Precast Wall = 13.32% completed
4 Interior work 2.69% Guest Room = 4.25% completed