Construction update February 2018

Construction update February 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 45.12 % of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 77.90% Basement 1 – 2 = 100% completed
1st floor = 90% completed
1st M - 7th floor = 100% completed
8th – 9th floor = 75% completed
9th M floor = 60% completed
10th – 31st floor = 100% completed
32nd M floor = 50% completed
34th – 36th floor = 100% completed
37th – 40th floor = 50% completed
2 Systems installation 27.07% Electrical and communication system = 22.14% completed
Sanitary, plumbing and fire protection system = 31.76% completed
Air conditioning and ventilation system = 30.81% completed
3 Architectural work 32.00% Public area = 47.59% completed
Common area = 17.61% completed
Guest Room = 56.85% completed
Façade – Precast Wall = 25.16% completed
4 Interior work 5.03% Guest Room = 7.93% completed