Construction update December 2017

Construction update December 2017

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 29.65 % of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 70.25% Basement 1 – 2 = 100% completed
1st floor = 90% completed
1st M - 7th floor = 100% completed
8th – 9th floor = 75% completed
9th M floor = 60% completed
10th – 31st floor = 100% completed
32nd M floor = 50% completed
2 Systems installation 13.80% Electrical and communication system = 7.36% completed
Sanitary, plumbing and fire protection system = 21.09% completed
Air conditioning and ventilation system = 22.90% completed
3 Architectural work 20.15% Public area = 34.83% completed
Common area = 14.42% completed
Guest Room = 43.46% completed
Façade – Precast Wall = 7.65% completed