Construction update December 2016

Construction update December 2016

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 5.91% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 18.46% soil protection work completed . In the process of foundation piling work
2 Systems installation - -
3 Architectural work - -