Construction update August 2018

Construction update September 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 72.20% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 98.98%% B1 & B2 floor = 100% completed
L1-L55 floor = 100% completed
L33 floor = 90% completed
Roof feature construction is 85% complete.
2 Systems installation 64.93% Electrical and communication system = 60.36% completed
Sanitary, plumbing and fire protection system = 69.27% completed
Air conditioning and ventilation system = 68.62%completed
3 Architectural work 61.59% Public area = 78.57% completed
Common area = 49.78% completed
Guest Room = 95.36% completed
Façade – Precast Wall = 44.75% completed
4 Interior work 50.25% Guest Room construction is 51.51%complete.
Public Area construction is 48.07% complete.