Construction update August 2017

Construction update August 2017

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 15.45% of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 48.66% Basement 1 – 2 = 100% completed
1st floor = 90% completed
1st M - 7th floor = 100% completed
8th – 9th floor = 75% completed
9th M floor = 60% completed
10th floor = 75% completed
11th – 17th floor = 50% completed
2 Systems installation 1.55% Electrical and communication system = 1.24% completed
Sanitary, plumbing and fire protection system = 2.50% completed
Air conditioning and ventilation system = 1.06% completed
3 Architectural work 2.05% Common areas = 5.34% completed
Façade – Precast wall = 0.54% completed