Construction update April 2018

Construction update April 2018

  • The environmental impact assessment has been approved.
  • Request for a construction permit has already been filed under section 39.
  • Expected Completion Date: May 2019
  • 47.45 % of Overall construction work completed

# Percentage Completed Construction Work Progress
1 Strutural work 85.95% Basement 1 – 2 = 100% completed
1st floor = 90% completed
1st M - 9th floor = 100% completed
9th M floor = 90% completed
10th – 41st floor = 100% completed
42nd floor = 50% completed
42nd M floor = 100% completed
43rd floor = 50% completed
44th floor = 100% completed
2 Systems installation 36.97% Electrical and communication system = 30.77% completed
Sanitary, plumbing and fire protection system = 44.34% completed
Air conditioning and ventilation system = 39.69% completed
3 Architectural work 41.29% Public area = 50.67% completed
Common area = 21.85% completed
Guest Room = 66.80% completed
Façade – Precast Wall = 39.57% completed
4 Interior work 15.54% Guest Room construction is 14.86% complete.
Public Area construction is 14.77% complete.